Installer Trainings
In-House Training Process
Contractors are welcome to come to Omega and receive on-site classroom training with our experienced technical team. This classroom training will include a page-by-page overview of Omega's installation manual. Contractors will review all aspects of pre-order procedures to identify all necessary information from the host pipe to accurately order your UV liner for your project.
Contractors will also review Omega's installation protocols, which list out host pipe preparation, cleaning/inspection, and required and recommended installation materials and tools. They then will move onto the step-by-step process of Omega UV Liner installation, insertion/removal of the UV light train, speed/temperature calibration during the curing process to end cutting, and removal of inner foil after the liner has been fully cured.
Other items, such as pulling methods, handling/disposal, and lateral reinstatements, will be reviewed within the installation manual. Once the classroom training of the manual has been completed, contractors then be trained on proper safety sleeve, light train, and can installation/removals as well as calibration techniques during the curing process.
On-Site Training
Omega also offers on-site training to new and existing contractors, whether a contractor is on their first UV liner project or to refresh an existing crew. Omega will come on-site to help assist and train to ensure crews efficiently and safely install an Omega UV liner. Training can take place for both laborers/groundsmen and the UV operators.
For more information, please reach out to our sales team.
Want to become a certified Omega Liner installer?
pre-installation planning topics
Technical and Financial Consulting
Crew Efficiency Evaluation and Training
Equipment procurement and finance sources/options
Tool and Equipment selection
Tool and Equipment Design
Large and bulk liner handling and logistics
UV Lining Safety
physical liner installation trainings
Host pipe preparation
Liner rigging
Manhole preparation
Winch/pulling set-up and safety
Liner installation
Can installation and liner end preparation
Light train installation/operation
Cable rigging and protection
Light train removal
Liner cutting and post-installation treatment
Foil removal and management
Lateral reinstatement (large diameter pipes)
post-installation instruction
Identifying defects, defect management and response
UV system maintenance and repair
Installation maintenance and repair
Post-lining upkeep and maintenance